Oluyole Fed Lawmaker Sadipe, Doctored Viral Video To Deceive Nigerians

0 311

The Management of DC Engineering Ltd handling the Ijebu Igbo-Ibadan Road project has denied attending any meeting in National Assembly or elsewhere in Abuja on Wednesday 13th September 2023, to tender an apology to the House of Representatives Member, representing Oluyole Federal Constituency of Oyo State, Tolulope Akande Sadipe, over inflation of contract from N9.8billion to N54billion.

 

Recall that, on Wednesday, an aide to Hon. Sadipe, one Olamilekan Olusada, sent out a press statement and edited video claiming that the management of DC Engineering was at a meeting with House of Representatives Adhoc Committee on Wednesday 13 September 2023, and tendered an apology to Sadipe over accusation of her alleged involvement in the re-award of Ijebu Igbo-Ibadan Road project from N9.8 billion to N54 billion.

Sarumi

In response to the claim by Hon. Sadipe’s office, the Executive Director of DC Engineering Ltd, Engr. Ade Adedeji, said: “There was never any Public Hearing by the House of Representatives Ad-hoc Committee on Wednesday 13 September, 2023 where we participated. No representative of DC Engineering Ltd was in any office at the National Assembly as regards the ongoing investigation on the Contract, Construction of Ijebu Igbo-Ibadan Road.

“The extracted video and news shared was only designed to misinform and divert the attention of Nigerians from the real issue. The matter is under investigation by the National Assembly Ad-Committee and we won’t comment on such. The distorted video was copy-cut-paste of the 7th September 2023 sitting of the House of Representatives probe panel.”

Monumental Legacy

Recall that last week Thursday, during an investigation by the House ad hoc committee investigating the slow pace of the Ijebu Igbo-Ibadan road project, there was an allegation that Reps Member connived with some officials of the Federal Ministry of Works to re-award an ongoing project to another contractor from its original contract sum of N9.8billion to N54billion.

Biiro D Solution

The company then said despite its request for an upward review of the project to at least N14 billion, the officials of the Ministry of Works ignored their request but went ahead to re-award the contract to another company, Areatech Construction Ltd at N54 billion.

Engr. Adedeji then told the committee that he had no personal issue with Sadipe but there was no how they would fold their hands and allow illegality to prevail.

The Director, Highways, South West, Federal Ministry of Works, Engr. Adedamola Kuti told the committee chaired by Hon. Kwamoti Bitrus Laori that they had terminated the contract of DC Engineering Ltd in September 2022 and re-awarded it to two other companies but he was silent on why the 41km road contract was reviewed from N9.8 billion to N54. billion.

It was learned that the project was awarded in 2018 and expected to be completed in 2020 but it took the Federal Ministry of Works five years 2018 to 2023 before paying 15% mobilization fees of N1.3 billion to DC Engineering Ltd leading to the slow pace of the project.

It was gathered that the Bureau of Public Procurement (BPP) which earlier gave a Certificate of No Objection, to Areatech Construction Ltd had since canceled it as the original contractor is still on site. BPP based its action on the ground that no project shall be re-awarded to another company without the termination of the initial contract.